About this calculator
A quick bid from your direct costs. For a full itemised quote with your logo, use Jobs.
How it’s calculated
Direct cost = materials + labour + other. Overhead is a percentage of direct cost. Profit is a percentage of direct cost plus overhead. Tax is added last.
Worked example
With these inputs:
- Materials
- R0
- Labour hours
- 48
- Labour cost per hour
- R94
- Equipment, subcontractors, skips, plan fees
- R0
- Overhead %
- 12%
- Profit %
- 15%
- VAT %
- 0%
the result is:
- Bid price
- R5,811.46
- Materials
- R0.00
- Labour
- R4,512.00
- Other direct costs
- R0.00
- Overhead
- R541.44
Tips from the trade
- Registering for VAT is compulsory once your taxable sales pass R2.3 million in 12 months. Until you are registered, leave VAT at 0 and charge none.
Results are estimates for planning and pricing. Check quantities against your drawings, the manufacturer’s data and SANS 10400 (the National Building Regulations) and your local municipality before ordering.