How much extra to allow for cutting, breakage and spillage in each trade, the allowances BouWise uses by default, and where makers publish their own.

Every material list needs a little more than the drawing shows. Concrete spills and sticks to the barrow, bricks break, tiles are cut, and boards are trimmed. The extra is the waste allowance, and getting it right is a balance: too little and the job stops while you fetch more; too much and the leftovers eat your profit. This guide sets out the allowances BouWise uses by default, why they differ by trade, and where a maker or industry body publishes its own figure.

Why waste differs by trade

Waste comes from three things: cutting, breakage and losses in handling or mixing. Concrete has no cutting but loses volume to uneven ground and spillage. Bricks are seldom cut but some break in delivery. Tiles and boards are cut at every edge, so the shape of the room and the layout matter more than the area. A small, awkward job always wastes a higher share than a large, simple one.

BouWise’s default allowances

TradeDefaultNotes
Concrete: slabs, footings, columns, steps10%Less on a neat, formed slab; more for hand-dug trenches
Bricks and blocks5%More for face bricks chosen for colour, or many openings
Mortar and plaster10%Droppings and mixing losses
Floor screed10%AfriSam’s own allowance for screed
Pavers10%The CMA’s allowance for cutting and waste, also for kerbs
Tiles7 to 20%By layout: straight 7 to 10%, diagonal 15%, herringbone 20%
RhinoBoard partitions12%Offcuts around doors and at the top of the wall
Ceilings5%Board lengths chosen to suit the room
Roof tiles10%Cuts at hips, valleys and verges, and breakage
Cladding planks and decking10%End cuts and splits
Skirting and trim15%Mitres and short pieces lost at every corner
Sand and topsoil10 to 15%Settling and compaction once spread

These are starting points, and every BouWise calculator lets you change them. Where a maker or industry body publishes a figure, use it: the CMA asks for 10% on pavers and kerbs, and AfriSam adds 10% to screed materials.

A worked example

A 16.2 m² bathroom floor in 300 × 600 mm tiles needs about 88.7 tiles with no waste. Laid straight with a few cuts, 10% brings it to 98. Laid diagonally at 15%, it is 102; in a herringbone at 20%, 107. The layout changes the order by nearly a tenth, which is why the tile calculator asks for it.

Rounding is a second allowance

Materials come in whole units: bags, sheets, boxes, cubes and tins. Rounding up to whole units adds a little extra on top of the waste allowance, sometimes a lot on small jobs. A slab needing 0.3 m³ of stone still means ordering a half cube. Keep that in mind before adding a big percentage as well; the rounding may already cover you.

When to allow more

  • Small jobs, where one broken unit is a larger share of the total.
  • Complicated shapes: many corners, curves, openings or angles.
  • Diagonal and herringbone layouts.
  • Materials you can’t easily match later, such as face bricks and tiles from one batch. A few spare is cheaper than a mismatch.
  • Inexperienced crews or difficult access.

When to allow less

  • Large, simple, repeated areas.
  • Formed concrete on a well-compacted, level base.
  • Materials that can be returned or used on the next job.

Waste on the quote

Price the waste into the job, don’t hide it. When you add a calculator result to a BouWise job, the quantities already include the allowance, and the quote prices them at your price-list rates. Keep a note of what was really used on each job; after a few jobs you will know your own waste rates better than any table.